28 Jun, 2017 | Written by Premis

Premis Update: Redcliffe Hospital MBICC

 

Premis Solutions is delivering a major upgrade to the Kidney and Cancer Care Ward at Redcliffe Hospital in Brisbane’s north.

Currently preparations are underway to pour level 4 and level 5 walls to the external new structure this week.   We are also weeks away from completing all 5 levels of the new exterior lift, stairwell and connecting decks to the main building.   Once completed Premis will commence the external cladding works.

We are pleased with the progress of the internal aspect of the project, and at this time, two of the three levels under refurbishment are being painted and joinery installations are almost complete.  Plumbing works are moving forward on the installation of the reverse osmosis renal dialysis system, and the cancer and renal care treatment bays are also taking shape.   Both floors will enjoy sweeping views of the Moreton Bay coastline.

Let's have a chat